# What Should a Grounding and Bonding Review Record?

Field Answers · Power & Electrical

What a data center grounding and bonding review should document, who should perform it, and why a visual check alone cannot confirm electrical integrity.

2 min read Power & Electrical Updated November 2026

On this page

1. [Short answer](https://datacentertraining.us/answers/grounding-bonding-inspection-records.html#answer)
2. [Why it matters](https://datacentertraining.us/answers/grounding-bonding-inspection-records.html#why)
3. [What to check](https://datacentertraining.us/answers/grounding-bonding-inspection-records.html#check)
4. [Example from the field](https://datacentertraining.us/answers/grounding-bonding-inspection-records.html#example)
5. [Related training](https://datacentertraining.us/answers/grounding-bonding-inspection-records.html#training)
6. [Follow-up question](https://datacentertraining.us/answers/grounding-bonding-inspection-records.html#faq)
7. [Sources](https://datacentertraining.us/answers/grounding-bonding-inspection-records.html#sources)
8. [Related questions](https://datacentertraining.us/answers/grounding-bonding-inspection-records.html#related)

[**Test yourself**Take the Power & Electrical quiz.](https://datacentertraining.us/quizzes/power-electrical-quiz.html)

**Short answer:** Grounding and bonding reviews should use qualified personnel, approved criteria, and traceable records; visual observations alone cannot establish electrical integrity.

## Why it matters

Incomplete records or assumptions about bonding can mask gaps in protection and make future changes harder to assess.

## What to check

- Use current drawings and acceptance criteria
- Identify the equipment and connection points reviewed
- Record test method and instrument details when applicable
- Route anomalies to the electrical authority

## Example from the field

A rack relocation changes the bonding path. The project lead updates the drawing package and has the designated qualified person verify the installation before closeout.

## Related training

The course on this site that covers this topic most directly is [Power Systems & Electrical Fundamentals](https://datacentertraining.us/courses/power-systems-electrical-fundamentals.html), part of the Power & Electrical Systems track. Use it for role-based familiarization or as refresher training alongside your site procedures.

### [Power Systems & Electrical Fundamentals](https://datacentertraining.us/courses/power-systems-electrical-fundamentals.html)

Power & Electrical · Comprehensive Program · NFPA 70E

Master data center electrical infrastructure — from utility interconnection to UPS and PDU architecture.

8 hrs

$303.99

- [Enroll](https://datacentertraining.us/checkout.html?item=power-systems-electrical-fundamentals)
- [Add to Cart](https://datacentertraining.us/cart.html?add=power-systems-electrical-fundamentals)

A certificate of completion is not a license or regulatory certification. It does not replace site-specific authorization, approved procedures, or task qualification, which your employer decides.

## Follow-up question

### Can a visual check confirm a grounding connection is adequate?

No. Visual review can identify obvious damage, but adequacy must be determined using approved methods by qualified personnel.

## Sources

- NFPA, [NFPA 70B, Standard for Electrical Equipment Maintenance](https://www.nfpa.org/codes-and-standards/nfpa-70b-standard-development/70b).
- NFPA, [NFPA 70, National Electrical Code](https://www.nfpa.org/codes-and-standards/nfpa-70-standard-development/70).
- OSHA, [29 CFR 1910.332, Electrical safety-related work practices: training](https://www.osha.gov/laws-regs/regulations/standardnumber/1910/1910.332).

## Related questions

[Answer](https://datacentertraining.us/answers/phase-imbalance-critical-load.html)

### What Should Data Center Teams Trend for Phase Imbalance?

Phase loading should be interpreted against equipment design limits, measurement context, and the facility's…

Read the answer →

[Answer](https://datacentertraining.us/answers/ups-load-bank-test-record.html)

### What Should a UPS Load Bank Test Record Include?

A useful UPS load-bank record ties the test objective to the approved plan, equipment configuration, readings…

Read the answer →

[Answer](https://datacentertraining.us/answers/electrical-room-housekeeping.html)

### What Does Good Electrical Room Housekeeping Look Like?

Electrical-room housekeeping means keeping access, work areas, equipment identification, and emergency routes…

Read the answer →

[Answer](https://datacentertraining.us/answers/ups-operating-mode-change.html)

### How Should a Data Center Control UPS Operating Mode Changes?

A UPS mode change should be treated as a controlled operational change with an authorized owner, understood…

Read the answer →

[Answer](https://datacentertraining.us/answers/generator-synchronization-parallel-operation.html)

### What Do Operators Need to Know About Generator Synchronization?

Parallel generator operation depends on coordinated electrical conditions and approved control logic…

Read the answer →

[Guide](https://datacentertraining.us/learn/data-center-power.html)

### Data Center Power Systems

The Knowledge Center guide for the Power & Electrical track.

Read the guide →

[See every Power & Electrical answer →](https://datacentertraining.us/answers/#power)

This answer is general educational information for data center facility teams, not a site procedure, engineering advice, or a compliance determination. Follow your approved procedures and the requirements that apply to your site. Last updated November 2026.

## Train Your Facilities Team

Self-paced online courses for data center technicians, engineers, and managers, with a certificate of completion for every course.

- [See Electrical Safety Training](https://datacentertraining.us/training/data-center-electrical-safety-training.html)
- [Browse All Courses](https://datacentertraining.us/courses.html)
- [Call 1-866-429-6742](tel:18664296742)

---

Markdown version of https://datacentertraining.us/answers/grounding-bonding-inspection-records.html · For AI agents: [llms.txt](https://datacentertraining.us/llms.txt) · [Developer portal](https://datacentertraining.us/developers/)